Sun City Limited commences construction of a multi-purpose water park on 1 July 2014 for Pretoria Limited. Sun City Limited signs a fixed-price contract for total revenues of $50 million. The project is expected to be completed by the end of 2017 and Pretoria Limited controls the asset throughout the period of construction. The expected cost as at the commencement of construction is $38 million. The estimated costs of a construction project might change throughout the project—in this example, they do change. The following data relates to the project (the financial years end on 30 June):

2015 ($m) 2016 ($m) 2017($m)
Costs for the year 10 18 12
Costs incurred to date 10 28 40
Estimated costs to complete 28 12
Progress billings during the year 12 20 18
Cash collected during the year 11 19 20

Required

(a)     Using the above data, compute the gross profit to be recognised for each of the three years, assuming that the outcome of the contract can be reliably estimated.  

(b) Prepare the journal entries for the 2015 financial year using the percentage-of-completion method.  

(c)  Prepare the journal entries for the 2015 financial year, assuming the stage of completion cannot be reliably assessed.  

Click on Buy Solution and make payment. All prices shown above are in USD. Payment supported in all currencies. Price shown above includes the solution of all questions mentioned on this page. Please note that our prices are fixed (do not bargain).

After making payment, solution is available instantly.Solution is available either in Word or Excel format unless otherwise specified.


If your question is slightly different from the above question, please contact us at info@myassignmentguru.com with your version of question.