Ola Ltd, which uses a job costing system, had two jobs in process at the start of the year: Job L1 ($68,000) and Job L2 ($30 000). The following information is available:

i. The company applies manufacturing overhead on the basis of machine hours. Budgeted overhead and machine activity for the year were anticipated to be $1,000,000 and 25,000 hours, respectively.

ii. The company worked on three jobs during the first quarter (i.e. from 1 January to 31 March). Direct materials used, direct labour incurred and machine hours consumed were as shown in the following table:

 

Job numbers Direct material Direct labour Machine hours
L1 $15,000 $30,000    900
L2      – 33,000 1,600
L3 45,000 65,000 2,000
       

 

iii. Manufacturing overhead incurred during the first quarter was $215,000. iv) Ola Ltd completed Job L1 and Job L2 during the first quarter. Job L2 was sold on credit, producing a profit of $30,000 for the company.

 

Required:

 

  1. Calculate the company’s predetermined overhead rate.
  2. Calculate manufacturing overhead applied to production for the first quarter.
  3. Determine the cost of jobs completed in the first quarter.
  4. Determine the cost of the jobs still in process at the end of the first quarter.

Click on Buy Solution and make payment. All prices shown above are in USD. Payment supported in all currencies. Price shown above includes the solution of all questions mentioned on this page. Please note that our prices are fixed (do not bargain).

After making payment, solution is available instantly.Solution is available either in Word or Excel format unless otherwise specified.


If your question is slightly different from the above question, please contact us at info@myassignmentguru.com with your version of question.